- The project is composed of Two basement floors for parking and electro-mechanical services, the area of each basement = 5,300 m2.
- The above ground office areas consist of ground floor plus 27 typical floors with a total floor area of 28,750 m2.
- The Contractual duration of the project is 20 months, but the actual duration of the project exceeded double it’s duration . The project suffered excessive delays, mainly due to contractor’s reasons.
- The Client requested our services to investigate the problems.
Dana Tower Project In Qatar
Project Details
EPM's CONTRIBUTIONS & SERVICES:
Claims Consultancy to include:
- Review all project Contracts and Documents to Assess the Client’s Contractual Status.
- Evaluate the Current Status of the Project, and Identify the Causes of Delays.
- Review the priced BOQ and actual work physically carried out on site.
- Assess both, Project Consultant and Contractor Performance during all Phases of the Project.
- Prepare detailed Claim Report Supported by all Contractual Documents.
- Recommend Further Procedures to Reimburse all Damages (arbitration or else as may be necessary).